Guide

Dual Septic and Greywater Systems on Rural NSW Properties

Hastings Septic Co is an independent referral service and does not perform or contract for the advertised work. Your enquiry may be referred to an independent contractor. Where licensing is required, the contractor's identity and licence details will be provided before you accept a quotation or enter a contract.

A dual system splits a property’s wastewater in two: toilet waste (blackwater) goes to a septic tank or aerated system, and some or all of the greywater from showers, basins and laundry goes to a separate greywater treatment system that can irrigate the garden. On unsewered land in NSW both halves need council approval, a manufactured greywater treatment system must be accredited by NSW Health, and both need ongoing servicing. It suits some rural blocks; on a tight lot one system for all wastewater is often simpler.

What counts as greywater

NSW definitions vary by document. The Easy Septic Guide (NSW Department of Local Government, 2000) defines greywater as wastewater from laundry and bathrooms “(and sometimes kitchen sinks)”, but not toilets. NSW Health’s 2005 greywater treatment system accreditation guideline includes the kitchen sink and dishwasher. NSW Health’s 2016 vessel accreditation guideline, which covers holding and settling tanks, says kitchen wastewater “is excluded from a greywater tank” and may only go to a septic tank or a common effluent pre-treatment tank.

So where the kitchen drains depends on the system chosen and its approval. Confirm it in the design, and make sure every plumber and service agent knows the layout. The greywater vs blackwater guide covers separating the two streams.

Approval and accreditation

  • Accredited treatment unit. NSW Health’s 2005 guideline says a council must not approve a manufactured domestic greywater treatment system unless NSW Health has accredited it. NSW Health’s register of accredited greywater treatment systems listed four certificates when checked.
  • Council approval for both parts. The same guideline says the owner must get prior council approval to install both the treatment system and its land application system, and an approval to operate for both.
  • The septic side. Installing or altering a septic system needs section 68 approval; Port Macquarie-Hastings Council takes applications through the NSW Planning Portal with a geotechnical wastewater report (PMHC, On-site sewage approvals). The PMHC septic approval process guide walks through it.

Diversion devices are not the same thing

NSW Health’s 2005 guideline defines a greywater diversion device as one that collects and directs untreated greywater to a sub-surface irrigation area or to the sewer, without storage. Its 2016 vessel guideline states that diversion devices installed under the Regulation’s diversion provisions “are not permitted in unsewered areas”. The state’s April 2025 Onsite Wastewater Management Guidelines put it differently: any greywater treatment, processing or diversion device in an unsewered area “requires approval by the council” (p.100). Either way, on a septic property greywater reuse needs council approval first, and a hose off the laundry tub is not an approved system; ask the council which devices it will approve.

Land and site limits

Each half needs its own approved land application area, with the separations to boundaries, buildings, bores and waterways that the council applies. The April 2025 OLG guidelines give buffer ranges from an effluent area of 50 to 100 metres to permanent surface water, 15 to 40 metres to farm dams and intermittent water bodies, and 15 to 100 metres to bores and wells (Table 4-2, p.62); the older Easy Septic Guide (2000) recommended 100, 40 and 250 metres respectively (p.28). Fitting two areas is easier on a large block than a small one; a wastewater consultant’s site assessment settles whether both fit.

An aerated wastewater treatment system (AWTS) is the main alternative: the Easy Septic Guide notes that aerated systems “may also be used to treat greywater” to a standard for watering non-food plants. One AWTS for all wastewater means one system to service instead of two.

Servicing both systems

  • Greywater treatment system. NSW Health’s 2005 guideline sets service at three-monthly intervals, or six-monthly where a remote monitoring program is installed, under a maintenance contract, with the service report sent to the council and the owner after each service.
  • AWTS on the blackwater side. Serviced at the interval on its certificate, with a service contract of at least 12 months and a report to council after every service (NSW Health, Secondary Treatment System Accreditation Guideline); see aerated system servicing.
  • Conventional septic tank. Still needs periodic pump-outs. With less water going in, check with the service agent how often the tank should be checked rather than assuming a longer interval.
  • Separate greywater tanks. The Easy Septic Guide recommends cleaning a greywater tank at least twice a year and releasing greywater within two hours, otherwise “it can go bad and smelly”.

Cost

No verified installed price exists for a dual system. The cost depends on the treatment unit, the two land application areas, re-plumbing the house to split the drains, and two lots of approvals and servicing. The septic pump-out cost guide lists the councils’ 2026-27 approval fees.

Dual septic and greywater FAQs

Can a greywater system be added to a house that already has a septic?

Yes, subject to council approval and enough land. The house drains must be split by a licensed plumber, and the treatment system and its irrigation area need their own approvals.

Does the greywater system need servicing as often as an AWTS?

Under NSW Health’s 2005 greywater guideline, every three months, or every six months with remote monitoring. Check the conditions on the specific system’s approval.

Can I run laundry water onto the garden with a hose?

Not without council approval. NSW Health’s 2016 vessel guideline says greywater diversion devices are not permitted in unsewered areas, and the April 2025 state guidelines say any greywater device in an unsewered area requires council approval, so ask the council before diverting any greywater.

What happens if the greywater system fails?

Stop irrigating with it and contact the service agent. Whether the septic can temporarily take the greywater depends on its capacity and the approval, so ask before redirecting flows.

Request a quote with the suburb, the current system and what is planned.

Sources

Last reviewed 16/11/2026. How these pages are researched and corrected.

More guides

Septic Tank Additives, Enzymes and Bacteria Products: An Honest Review

Do septic tank additives, enzymes, bacteria products or yeast work? What NSW guidance and local councils actually…

View

Emergency Septic Overflow: Health Risks, Contamination and What to Do

Why septic overflow is a health risk, what to do first, how NSW Health advises cleaning sewage-contaminated surfaces,…

View

Failed Absorption Trenches: How to Diagnose and Fix Septic Field Failure

Soggy ground, smells and slow drains can mean failed septic absorption trenches. How to tell, what causes the…

View

More on this topic

Request a quote

Tell us about the job and an independent local contractor can quote it.