A septic system that takes wastewater from more than one dwelling has to be designed, approved and maintained for the combined load of everyone connected to it, not just the house it was first built for. Under the NSW Government’s 2025 guidelines for councils, a building with its own toilet and laundry counts as a separate household, so a granny flat or second house adds a full household’s load to the design. Problems usually start when that second dwelling is plumbed in years later without anyone checking the system.
What counts as a shared system?
Any on-site system receiving wastewater from more than one dwelling is shared. Common examples:
- a granny flat or secondary dwelling plumbed into the main house’s tank
- a dual occupancy with two dwellings on one tank and one effluent area
- a second or third house added to an acreage block over the years
- several cabins or cottages on one rural title draining to one system
The tank and effluent area do not know how many kitchens feed them; they respond to the total volume arriving each day.
How the combined load is worked out
The NSW Office of Local Government’s Onsite Wastewater Management Guidelines (April 2025, section 6.1) size systems on daily load: design occupancy, in equivalent persons (EP), multiplied by a design flow allowance per person.
- Occupancy comes from bedrooms, not residents: 3 EP for one bedroom, then one more per bedroom (a three-bedroom house is 5 EP), unless the council sets its own figures.
- Each building with its own toilet and laundry is a separate household, so its occupancy “would start at 3EP”.
- Flow allowance: 120 litres per person per day on tank water, 150 on reticulated or bore water.
- Minimum septic tank size rises with occupancy: 2,750 litres for 5 EP and 4,400 litres for 8 EP (Table 6-3).
As an illustration of that method, not a design: a three-bedroom house (5 EP) plus a one-bedroom granny flat (3 EP) is 8 EP, or 960 litres a day on tank water, against 600 litres a day for the house alone. The effluent area is usually the tighter limit, because it was sized for the original load on that site’s soil; a site and soil assessment shows whether it can take more.
The approval covers the whole system
Installing or altering a system needs council approval: Port Macquarie-Hastings Council says “You will need a Section 68 approval to install, construct or alter” a waste treatment device (PMHC, On-site sewage approvals), and MidCoast Council says the same for installing or altering a septic system. The 2025 Guidelines tell councils that existing systems need not meet current design standards unless the system fails or there is “an alteration to the buildings associated with the system”. Adding a dwelling alters the buildings the system serves, so council may require the combined system to meet current standards; ask council before relying on the old design.
The Guidelines’ model council strategy also asks applicants for floor plans showing every bedroom, “including any secondary dwellings such as granny flats”. Raising the wastewater side with council before the second dwelling is approved and built avoids finding out at settlement that the system was never approved for it.
Maintenance and responsibility between households
More people on one tank means solids build up faster. Kempsey Shire Council’s septic checklist says pump-out frequency “will vary depending on the number of occupants”, so the interval that suited one household will not suit two.
Where households share a system, settle these early:
- Who books and pays for pump-outs and servicing, ideally in writing.
- Whose name the approval to operate is in. Port Macquarie-Hastings Council asks new owners to apply for approval to operate “within 3 months of property transfer”.
- Access across titles. Where a tank sits on one title and serves a dwelling on another, whether an easement or a registered agreement is needed for access and maintenance is a question for a conveyancer or solicitor.
A system that collects partly treated wastewater from several separate properties and pipes it to a central facility is a common effluent system, a different arrangement: the Guidelines say its owner or operator “must obtain approval under the LG Act or a WICA licence”.
Frequently asked questions
Can I connect a granny flat to the existing septic tank?
Not without checking first. Under the 2025 Guidelines a granny flat with its own toilet and laundry adds at least 3 EP to the design load, and connecting it is an alteration that needs council approval, so have the system’s capacity assessed and talk to council before connecting.
Does a shared system need pumping more often?
Generally yes, because more occupants put more solids into the same tank. Kempsey Shire Council says frequency varies with the number of occupants, so base the schedule on the combined household, not the original one.
Is a shared system the same as a dual occupancy system?
A dual occupancy is one common kind of shared system. The dual occupancy septic guide covers that case, and the tiny home septic guide covers small second dwellings.
Request a quote for an inspection with the number of dwellings, bedrooms in each and any approval paperwork you hold; the septic inspections page explains what a check covers, and council fees are in the septic pump-out cost guide. The enquiry may be referred to an independent licensed contractor who quotes in their own name.
Sources
- NSW Office of Local Government, Onsite Wastewater Management Guidelines (April 2025): design occupancy, flow allowances, tank sizes, existing systems, common effluent systems, checked 15/11/2026
- Port Macquarie-Hastings Council, On-site sewage approvals: section 68 approval and approval to operate for new owners, checked 15/11/2026
- MidCoast Council, On-site wastewater management: approval to install or alter, checked 15/11/2026
- Kempsey Shire Council, septic system checklist: pump-out frequency and occupants, checked 15/11/2026